Ambania Gas Compressor Station

Earthworks

Scope included:

  • Strip top soil and stockpile for re-use

  • Construct village pad

  • Construct temp site main and secondary laydown

  • Foundation compaction in fill areas

  • Supply and place culvert crossings

  • Main pad earthworks

  • Road earthworks

  • Construct cut off drains

  • Install grass roots

  • Install non grouted Rip Rap

  • Install grouted drainage outlets

Project Value: $1.86million

Project Completion: July 2022

Lise Doyle