Juwi Solar Farm, Ellendale
Earthworks
Scope included:
HV – South Feeder Trench
Fibre Optic Trench
Push up gravel in burrow pits
Access Rd grading and remediation works
HV – Combined trench
HV – Combined trench to substation
Remediation of North & South gravel burrow pits & sand pit
DC trench PCS-02-N
PCS inverters (1-8) backfill
Combiner boxes backfill
North & south block spoil removal
Met station 1 & 2 trenching & backfill
PCS fingers backfill, trim and cleaning
Stabilised sand and gravel crowns at Inverters 1-8
BOP Kiosk pad at substation with blue-metal install
Completion of O&M civil scope
Spares shed groundworks and pad
Spare shed ramp – taper earth
Road works in north block
Road works in south block
Compaction testing in trenches, road crossings and externals
Project value: $0.5m
Completion date: January 2020