Completed Project - Norton Gold Fields Binduli Mine Site
Scope of bulk earthworks carried out at Binduli Gold Mine:
Construction of 10 additional heap leach pads
Construction of one sediment control pond
Construction of one emergency pond
The 6 month contract started in June 2024.
Project completed: Mid December 2024
Contract value: $25m