Completed Project - Wonmunna Mine Site Intersection
Working directly for ASX 200 listed Mineral Resources, RDH is delivering the intersection of the Wonmunna Mine site access road and the Great Northern Highway, approx. 90KM north of Newman. With iron ore prices at all time highs, RDH are working closely with the client to ensure that the 24/7 ore road deliveries to Port Hedland are not being compromised through the delivery of scope. To do this RDH is providing 24/7 traffic control at the works sites that mange the ingress and egress of the quad road trains to and from Great Northern Hwy without affecting other road users in the area.
Works involve construction of a 2km acceleration lane, 900m passing lane and improved junction into the Wonmunna mine site from the Great Northern Highway at SLK 1250.90.
Other works include:
Culvert extensions from 5-barrel RBC 2400 x 1800 to 600 single barrel CSP including head walls and rock pitching.
Clearing and Grubbing
Foundation prep, embankment construction and subgrade preparation
Cut, load & haul and fill activities – site won and from borrow
Excavation and breaking out of rock.
Subbase and base course construction
Management of Seal & Asphalt contractors
Line marking, street furniture signage and installation of 10m solar lights.
Traffic management throughout project night and day (24/7 as mine is hauling ore 24/7)
Project management, supervision, and engineering
Project value circa $5m
Subcontract management $2.75m
Completion date August 2021