Main Roads WA
South Western Highway - shoulder improvement & sealing
Scope included:
Clearing as per clearing plan
Pavement construction
Cart and side cast gravel direct from trucks
Balance gravel to appropriate thickness using a grader
Light roll using a smooth drum roller to provide a firm track for the Graderliser
Mixing and conditioning to agreed depth
Testing to ensure specified compaction is achieved
Trimming of compacting of gravel within tolerances
Final roll using a final trim grader and multi wheel roller
Manage sealing & linemarking contractor
Project value: $2.33M
Completion date: end January 2024.